This master reference is essential if you contract with the government! Correctly pricing your goods or services—and making certain that those prices are in compliance with myriad federal rules and regulations—is essential to doing business with the government…and ensuring your commercial success. Cost-Based Pricing: A Guide for Government Contractors shows you how to appropriately estimate and price for government contracts and defend those estimates in a government contracting and subcontracting environment. This practical book includes coverage of all government pricing rules and regulations as well as pertinent aspects of related laws, such as the Truth in Negotiations Act. The book walks you through every step of the estimating process. From figuring direct labor costs to intra-company transfers to contract modifications, the coverage is extensive yet accessible for even those new to the process. Using Cost-Based Pricing, you will be able to: Develop more realistic estimates Enhance your support of those estimates in negotiations Avoid violations of the Truth in Negotiations Act Increase your chances of securing a fair and reasonable price Cost-Based Pricing: A Guide for Government Contractors can make the difference between your success—and profitability—and failure in the federal government arena.
Orders of 10+ copies shipping to one address receive free ground shipping
within the U.S. Shipping to separate individual addresses via USPS media mail will be applied a handling fee:
Book Details
Overview
This master reference is essential if you contract with the government! Correctly pricing your goods or services—and making certain that those prices are in compliance with myriad federal rules and regulations—is essential to doing business with the government…and ensuring your commercial success. Cost-Based Pricing: A Guide for Government Contractors shows you how to appropriately estimate and price for government contracts and defend those estimates in a government contracting and subcontracting environment. This practical book includes coverage of all government pricing rules and regulations as well as pertinent aspects of related laws, such as the Truth in Negotiations Act. The book walks you through every step of the estimating process. From figuring direct labor costs to intra-company transfers to contract modifications, the coverage is extensive yet accessible for even those new to the process. Using Cost-Based Pricing, you will be able to: Develop more realistic estimates Enhance your support of those estimates in negotiations Avoid violations of the Truth in Negotiations Act Increase your chances of securing a fair and reasonable price Cost-Based Pricing: A Guide for Government Contractors can make the difference between your success—and profitability—and failure in the federal government arena.
About the Author
Darrell J. Oyer (Author)
Darrell J. Oyer, CPA, is president of Darrell J. Oyer Co., a consulting firm that provides services and training to government contractors and federal government employees. His wealth of experience includes developing and reviewing contractor estimating systems, cost accounting structures, and cost control systems to ensure compliance with federal procurement requirements. Previously he was a partner in the Deloitte & Touche government contracts advisory practice and worked for the Defense Contract Audit Agency and the U.S. Air Force Auditor General's office. He is also the author of Pricing and Cost Accounting: A Handbook for Government Contractors, Third Edition, from Management Concepts Press.
Excerpt
Cost-Based Pricing: A Guide for Government Contractors
CHAPTER 1
Pricing Concepts
The pricing method preferred by the Federal Acquisition Regulation (FAR) is cost-based—in other words, the detailed, grassroots, or bottom-up approach. This method segregates activities with costs into their smallest component tasks, which are then supported with details such as bills of materials, hours (based on history), or work-measurement standards and rates based on historical rates. Price proposals based on cost estimates require an evaluation by the government customer—in the Department of Defense (DoD), by either the Defense Contract Audit Agency (DCAA) or the Defense Contract Management Agency (DCMA). Government evaluations of price proposals are frequently referred to as audits and are based on the FAR—Part 15 for pricing, Part 30 for cost, Part 30 for Cost Accounting Standards, and Part 31 for cost allowability.
Pricing encompasses all of a contractor’s activities in offering a price to the government customer. Pricing considerations include market research, cost estimates, market conditions, market objectives, long-range contractor plans, and contractor workload. The focus of this book is on the cost-estimating aspect.
Cost-based pricing is used in all cost-reimbursement contracts, where the price is based on an after-the-fact audit of actual cost. Variations of cost-type contracts include cost-plus-fixed-fee, cost-plus-incentive-fee, cost-plus-award-fee, cost sharing, cost (only), and the “materials” portion of a time-and-materials contract. Cost-based pricing also is used in negotiated fixed-price contracts, where the price is determined not by competition but by negotiation based on estimated cost (or on actual cost if the work has already been performed). Variations of fixed-price-type contracts include firm-fixed-price, fixed-price-incentive-fixed, fixed-price-award-fee, fixed-price with successive targets, fixed-price redeterminable, labor-hour contract, and the “labor” portion of time-and-materials contracts.
COST-BASED PRICING
Cost-based pricing differs from other pricing techniques in several ways. Cost-based pricing uses actual or estimated costs to determine the price of a government contract. Price is established by adding a profit or fee to these actual or estimated costs. Compared with market-based pricing, cost-based pricing is much more difficult to perform and subject to many more regulations. For example, the cost principles in FAR Part 31 apply when using cost-based pricing. Profit or fee is not significantly subject to regulation but is more prominently influenced by federal agency guidelines on negotiating profit or fee. Some legislated fee limits exist for cost-plus-fixed-fee contracts and for architect-and-engineering contracts; existing regulations do not address what fee a contractor may request but do provide guidelines to the government contracting officers. In market-based pricing, cost allowability and profit levels are irrelevant in that the price is assessed by the potential customer in terms of value received by purchasing the goods or services rather than by the cost (or estimated cost) to the seller.
By contrast, market-based pricing consists of a single figure for the price, which the buyer evaluates based on the perceived benefit or value received. The estimated cost and the amount of profit are irrelevant to the buyer’s decision; the value of the goods is simply assessed and compared to the price by the buyer. Prices of competitors’ products and services might be also compared in this decision process. In addition, completely different alternative solutions can be compared to one another.
Exhibit 1-1 shows the distinction between market-based and cost-based pricing.
EXHIBIT 1-1: Market-Based Pricing and Cost-Based Pricing
In accordance with FAR Part 15, cost-based pricing is a structured pricing approach that is based on FAR-determined cost elements. Cost elements are the components of an estimated cost and consist of direct labor (Chapter 2), materials and subcontracts (Chapter 3), indirect costs (Chapter 4), other direct costs (Chapter 5), and facilities capital cost of money (Chapter 5). Chapter 7 addresses the topic of profit or fee.
Need for Cost-Based Pricing
Cost-based government contract pricing has its origins in World War I. Before that time, the federal government purchased goods and services mostly available to the general public—horses, guns, wagons, foodstuffs, and so on. The need to design and build advanced, technological, and highly specialized war machinery—such as tanks and airplanes—not sold to the general public caused a shift to cost-based pricing, for good reason. If a company had had to accept a firm-fixed-price contract to design and build the first United States government–purchased tank, the price would have been exceptionally high due to the uncertainties of production cost, technological feasibility, production quantity, and price stability of materials. Sellers would have had to include substantial contingencies to be assured of a profitable contract. Setting the price at allowable cost plus a fixed fee removed enough risk from the seller that the total price was much less than that for a fixed-price contract.
Note the use of the word allowable to describe reimbursed costs in the previous paragraph. Clearly, the government did not want to give any contractor a blank check. Certain costs were considered to be not reimbursable due to public policy. Thus, FAR Part 31 now provides detailed guidance on what costs are unallowable. For example, entertainment costs are unallowable because “entertaining” government officials is not allowed; thus, taxpayer money should not be paid to contractors to cover costs of entertainment.
Often cost-reimbursement contracts are rightly criticized as not providing an incentive for a contractor to reduce costs, because cost reductions result in a lower price for the next sale and less profit. This is a valid criticism, but this contract type still has value for certain procurements where the risk under a fixed-price contract is so great that the resulting prices would be extremely high.
Work Breakdown Structure
When cost-based pricing is used, the work breakdown structure concept is often needed to adequately apply cost-based pricing techniques. This concept was developed in 1957 by DoD as part of the program evaluation and review technique (PERT). PERT did not use the term work breakdown structure. However, PERT was the forerunner of the work breakdown structure; PERT-Cost was the forerunner of earned value management systems, and PERT-Time was the forerunner of the critical path method. The term work breakdown structure was first used in 1968 in a DoD document, “Work Breakdown Structures for Defense Materiel Items” (MIL-STD-881). The general purpose of these various techniques was to allow accurate and timely estimating of the cost of a program at completion. DoD in particular has been plagued by programs experiencing surprise cost overruns. The DCMA Web site (www.dcma.mil) contains useful information on the government review of earned value management systems.
A work breakdown structure is developed by starting with the end objective and successively subdividing it into manageable components (i.e., in terms of size, duration, and responsibility) that include all steps necessary to achieve the objective. The work breakdown structure provides a common framework for the natural development of the overall planning and control of a contract and is the basis for dividing work into definable increments from which the statement of work or statement of objectives can be developed and technical, schedule, cost, and labor-hour reporting can be established. A work breakdown structure permits summing of subordinate costs for tasks, materials, and so on into their successively higher-level parent tasks and materials. For each element of the work breakdown structure, a description of the task to be performed is generated.
A work breakdown structure is organized around the primary products (or planned outcomes) of the project instead of the work needed (or planned actions) to produce the products. Since the planned outcomes are the desired ends of the project, they form a relatively stable set of categories in which to collect the costs of the planned actions needed to achieve them. A well-designed work breakdown structure makes it easy to assign each project activity to one—and only one—terminal element. In addition to its function in cost accounting, the work breakdown structure also helps map requirements from one level of system specification to another.
PARAMETRIC ESTIMATING
Parametric estimating techniques use a statistical relationship between historical data and other variables (e.g., square footage in construction or lines of code in software development) to calculate an estimate. Parametric estimates of cost-to-cost relationships have been used for many years. Some examples are scrap costs to a priced bill of materials, non-touch labor to touch labor, sustaining engineering to initial engineering, and even other direct costs to direct labor costs.
In the mid-1950s, Rand Corporation in Santa Monica, California, developed the most basic tool of the cost-estimating discipline, the cost-estimating relationship, and merged this concept with the learning curve (discussed in Chapter 10) to form the foundation of aerospace parametric estimating. Rand derived cost-estimating relationships for aircraft cost as a function of such variables as speed, range, and altitude (known as AMPER Weights).
In the late 1970s, parametric models were expanded into two additional aspects. First, models were developed based on relationships of cost to noncost variables, such as feet of wiring in an aircraft. The mathematics and logic are basically the same as for cost-to-cost relationships. Second, models were developed to estimate the cost of an entire product rather than individual elements of cost for that product. For example, the speed of an aircraft, the weight of the aircraft, expected labor escalation, complexity compared to previous aircraft, and so on would be entered into the “black box” of a parametric model and the resulting answer would be a bottom-line estimate for the product. Proponents of this technique believe this approach can produce higher levels of accuracy, depending on the sophistication of the model and the underlying data built into the model, than the traditional grassroots buildup approach.
A popular initial software package called RCA Price was developed in the late 1960s by PRICE Systems, a cost-analysis unit of RCA. Through mergers and acquisitions, PRICE Systems successively became part of GE Aerospace, Martin Marietta, and Lockheed Martin. A management buyout from Lockheed Martin in 1998 formed the independent company known today as PRICE Systems, LLC. Other parametric software is available from several companies: SLM-Estimate; WinEstimator, Inc.; CostWorks RSMeans; SmartBidNet; PlanSwift; SEER; and d-tools.
The DCAA believes that parametric estimating techniques based on cost-estimating relationships are acceptable in the appropriate circumstances for proposing costs on government contracts and issued audit guidance on parametric systems as early as 1978. The DCAA criteria for a valid parametric estimate are:
Logical relationships. Contractors are expected to demonstrate that cost-to-noncost estimating relationships are logical. DCAA’s primary concern in this area is that contractors consider all reasonable estimating alternatives and do not use only the first apparent set of variables. Contractor analysis may disclose multiple alternatives that appear logical; statistical testing should be used to help identify the best choice.
Significant statistical relationships. Contractors are also expected to demonstrate that a significant statistical relationship exists among the variables used in a parametric cost-estimating relationship. Several statistical methods, such as regression analysis, graphic analysis, statistical sampling, and learning curves, can be used to validate a cost-estimating relationship; however, no single uniform test can be specified. Statistical testing may vary depending on an overall risk assessment and the unique nature of both a contractor’s parametric database and the related estimating system. Proposal documentation should describe the statistical analysis performed, including the contractor’s explanation of why the cost-estimating relationship is statistically valid.
Verifiable data. There must be a system in place for verifying data used for parametric cost-estimating relationships. In many instances, the reviewer will not have previously evaluated the accuracy of noncost data used in parametric estimates. To monitor and document noncost variables, contractors may need to modify existing information systems or develop new ones. Information that is adequate for day-to-day management needs may not be reliable enough for contract pricing. Data used in parametric estimates must be accurately and consistently available over a period of time and easily traced to or reconciled with source documentation.
Reasonably accurate predictions. The contractor’s demonstration that the parametric cost-estimating relationships it used predict costs with a reasonable degree of accuracy is important. If the contractor’s analysis of historical estimating and cost-performance data shows that the parametric estimating system is as accurate as a discrete estimating system, then the government has increased assurance of receiving a fair and reasonable price. As with any estimating relationship derived from previous history, it is essential for the contractor to document that the work being estimated with parametric cost-estimating relationships is comparable to the previous work from which the parametric database was developed.
Proper system monitoring. A contractor should also ensure that cost-to-noncost parametric rates and factors will be monitored periodically in the same manner as is expected for cost-to-cost rates and factors. Because of improved technology, production changes, or better pricing alternatives, cost-estimating relationships can and do change. The contractor should be prepared to revalidate a parametric cost-estimating relationship whenever system monitoring discloses that the relationship has changed.
DCAA believes parametric estimating approaches are acceptable when they are properly implemented. The reviewer encounters it most often as a technique used in conjunction with other estimating methods; the majority of audited proposals are not developed solely on the basis of parametric estimating techniques. For example, parametric techniques are often used for estimating costs of scrap and other such factors. The use of parametric estimating is most appropriate in such circumstances where historical data are not available, as when the program is at the engineering concept stage or when no bill of materials exists and the program definition is unclear. Contractors with good parametric cost-estimating systems analyze their draft or tentative proposal to determine the appropriate estimating technique for each part of the work breakdown structure.
Contractors should be satisfied that implementation and monitoring costs required to apply a parametric model do not outweigh the benefit of reduced administrative estimating costs due to use of parametric estimating techniques. Moreover, it is critical that the environment is appropriate for the use of parametric techniques; it would not be prudent to rely exclusively on parametric techniques to estimate costs when directly applicable historical cost data are available. Such is the case in follow-on production for the same or similar hardware. Contractors manufacturing mature weapon systems already have a record of the actual costs. The use of parametric estimating may be appropriate for certain aspects of follow-on production; however, the contractor should disclose any data that may have a significant impact on cost. The exclusive use of parametric models is generally not appropriate for economic forecasting of such elements as labor and indirect-cost rates. For parametric estimates, the contractor must ensure that any changes in accounting practices are accounted for in the estimate and that labor and indirect-cost rates are appropriately applied.
SHOULD-COST PRICING
Should-cost reviews are a specialized form of cost analysis. Although described in FAR Part 15, should-cost reviews are no longer common. Should-cost reviews differ from traditional evaluation methods in that they do not assume that a contractor’s historical costs reflect efficient and economical operation. Instead, these reviews evaluate the economy and efficiency of the contractor’s existing workforce, methods, materials, equipment, real property, operating systems, and management. These reviews are accomplished by a multifunctional team of government contracting, contract administration, pricing, audit, and engineering representatives. The objective of should-cost reviews is to promote both short- and long-range improvements in the contractor’s economy and efficiency to reduce the cost of performance of government contracts. In addition, by providing a rationale for any recommendations and quantifying their impact on cost, the government will be better able to develop realistic objectives for negotiation.
The two types of should-cost reviews are program should-cost review and overhead should-cost review. A program should-cost review is used to evaluate significant elements of direct costs such as materials and labor as well as the indirect costs usually associated with the production of major systems. When a program should-cost review is conducted relative to a contractor proposal, a separate audit report on the proposal is required.
An overhead should-cost review is used to evaluate indirect costs, such as fringe benefits, shipping and receiving, real property and equipment, depreciation, plant maintenance and security, taxes, and general and administrative activities. It is normally used to evaluate and negotiate a forward pricing rate agreement with the contractor. When an overhead should-cost review is conducted, a separate audit report is required.1
OTHER PRICING AND ESTIMATING METHODS
Another estimating method is the comparative technique, which develops proposed costs using the costs for like items produced in the past as a baseline. Allowances are made for product dissimilarities as well as changes in such variables as complexity, scale, design, and materials by use of complexity factors, introduced in Chapter 2. A second technique is the judgmental method, which is a subjective estimation of costs using estimates of previous experience, judgment, memory, informal notes, and other data. It is typically used during the research and development phase when drawings have not yet been developed. A third technique is roundtable or estimating by consensus, whereby personnel from various disciplines discuss pricing, exchange views, and reach a consensus. Other commercial techniques focus on market pricing and may also include the above techniques, as addressed in Chapter 11.
Notes
1. A seldom-used DoD overhead analysis technique is probability of incurring estimated costs (PIECOST), developed by Otto Martinson in the late 1960s, the same time that should-cost pricing was developed.
Thank you for ordering a digital copy of this title. This will be delivered via email after checkout. Please refer to our Information About E-Books page for any further questions on formats, rights and compatible devices.
Thank you for requesting an exam copy. If you would like to request additional exam copies, please click on ‘Continue Shopping.’ Please limit your requests to not more than three books at a time. If not, please go to ‘Checkout’ and fill in your information and complete your request.